Wp6 Internal Planning

July-Sep 2016 Planning

  • 2016-07-11 Delivery of internal integration testing / development infrastructure by UoA.
  • 2016-07-15 Confirmation of functionality to be covered by VREs.

    • VRE 6.1:
    • Data entry
    • KPIs modeling (FCR and SFR) in company level
    • Site Description Management
    • Model Management
    • What-If Analysis Management
    • Production benchmarking (tentative)
    • Technoeconomic benchmarking (tentative)
    • VRE 6.2:
    • Project management
    • Geospatial rendering
    • Preliminary results rendering
    • Custom data import
    • Platform showcasing model (not integrated with T6.1)
    • Baseline execution platform
  • 2016-07-15 Confirmation of datasets to be utilized by VREs.

    • NUTS Classification data set
    • Compensation of employees by NUTS 2 regions (nama_10r_2coe)
    • Business demography by size class and NUTS 3 regions (bd_size_r3)
    • Employer business demography by NACE Rev. 2 and NUTS 3 regions (bd_enace2_r3)
    • Employer business demography by size class and NUTS 3 regions (bd_esize_r3)
    • Information regarding the land cover in Greece
    • Periodic (Sampling To Sampling) datasets. Each Aquaculture company provides each own datasets.
    • KPIs Table datasets which are generated by modeling the periodic datasets
    • Global KPIs Table datasets which are generated by the combination of periodic datasets from the appropriate companies
  • 2016-07-25 Internal release of Geopolis project management features (development infrastructure).

  • 2016-07-25 Launch of dataset publication into the infrastructure (Geoserver / Geonetwork).

  • 2016-09-10 Completion of initial dataset publication into the infrastructure.

  • 2016-09-10 Request of the creation of the VREs

  • 2016-09-30 Delivery of T6.1 and T6.2 software for deployment on pre-production.

  • 2016-10-31 Moving to pre-production after fixes and comments.