WP6 M03 Monthly Progress Report (Nov 2015)

Links: WP Issue: [#654]. Previous month: WP6-M02-MonthlyProgressReport. Next month: WP6-M04-MonthlyProgressReport

Note: Use bullets in sections

WP Summary

  • Completed VRE implementation plan milestone and applied in redmine system
  • Evolved the concepts VRE definition through meetings and discussions.
  • First round of requirements elicitation (preliminary user involvement included)
  • Updated concepts of the system (models, data set types etc)
  • Discussion on data management issues
  • Alignment of T6.1 and T6.2 activities (timeline and form of models, exchange of tools)
  • Analysis of opportunities for providing Blue Skills training tools
  • Supporting I2S update of the platform (UOA)
  • Experimentation with Spark exploitation and deployment
  • Launch of design of various platform elements (spark abstractions, geo-servers)
  • Checking of data sets identified
  • Benchmarking VRE design evolution to cover main system entities / System functionality / User interface design / Technology integration concept
  • Progressed on the field of implementing and deploying a proof of concept application in the infrastructure (I2S)
  • First Draft of Design Document of Benchmarking VRE
  • Progress to Blue Economy data set identification discussion
  • Removal of proprietary code from GeoPolis for publication as FOSS - to continue until the release of the s/w as EUPL 1.1 (CITE)
  • Cluster deployment planning (Spark & NoSQL clusters) (CITE)
  • Spark Cluster deployment (in progress) (CITE)
  • Evaluation of available Eurostat datasets (in progress)

T6.1 Performance evaluation, benchmarking and decision making in aquaculture VRE

Note: To be completed by Task Leader

Progress of Work

UOA

  • Contribution to VRE Definition
  • Requirements elicitation
  • VRE implementation plan contribution
  • Supporting I2S update of the platform
  • Contribution to data set analysis

I2S

  • first round the elicitation process of user requirements
  • Main system entities
  • System functionality
  • User interface design
  • Technology integration concept
  • Progressed in the objective to implement and deploy a proof of concept application on the VRE
  • First Draft of Design Document
  • Contribution to Blue Economy data set identification discussion

Deviations from plans and corrective actions

UOA

none

I2S

none

Plans for next month

  • Note: add any short term plans for the activity*

UOA

I2S

  • Advance the system design
  • Deploy proof of concept application in the VRE

Risks

  • Note: identify any new, rising or diminishing risks*

T6.2 Strategic Investment analysis and Scientific Planning/Alerting VRE

Note: To be completed by Task Leader

Progress of work

UOA

  • VRE implementation plan managed and applied in redmine
  • Requirements elicitation
  • Experimentation with Spark model representation
  • Launch of design of platform elements
  • Checking of data sets pointed out by WP partners

CITE

  • Removal of proprietary code from GeoPolis for publication as FOSS (will continue until the release of the s/w as EUPL 1.1)
  • Cluster deployment planning (Spark & NoSQL clusters)
  • Spark Cluster deployment (in progress)
  • Evaluation of available Eurostat datasets (in progress)
  • Contribution to Blue Economy data set identification discussion
  • Contribution to VRE Plan
  • Basic pre-evaluation of technologies / approaches for addressing challenges of the VRE

I2S

  • Contribution to Blue Economy data set identification discussion
  • Contribution to VRE Plan

FAO

Deviations from plans and corrective actions

Note: if any. Use bullets. Any references to partners should be in a parenthesis at the end of the bullet

UOA

none

CITE

none

I2S

none

FAO

none

Plans for next month

Note: add any short term plans for the activity

UOA

CITE

I2S

FAO

Risks

Note: identify any new, rising or diminishing risks

Meetings