Risk #984

8. Delays in production of deliverables, be it interim ones (with dependencies) or final ones

Added by Pasquale Pagano about 4 years ago. Updated over 1 year ago.

Status:ClosedStart date:Oct 12, 2015
Priority:HighDue date:Feb 28, 2018
Assignee:Leonardo Candela
Reference Reporting Period:1 Applied Mitigation:Yes
Risk Probability Rank:High Risk Materialized:Yes
Milestones:
Duration: 623

Description

Proposed Risk-Mitigation Measures
A structured process of activity progress monitoring and deliverables production is in place. Apart from the bodies performing this activity, instruments and deliverable types allow partners to be aware of upcoming delays, and confront them with a variety of means. Deliverables with significant dependencies are handled as priority. Furthermore, secondary plans are also considered: e.g. WP5-WP8 alternative routes for VRE implementation are considered, allowing inter VRE dependencies to not block other VREs.


Related issues

Related to BlueBRIDGE - Project WP #591: WP1 - Project Management [Months: 1-30] Closed Sep 01, 2015 Mar 19, 2018
Related to BlueBRIDGE - Project WP #602: WP2 - Project Governance, Exploitation and Sustainability... Closed Sep 01, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #612: WP3 - Communication, Stakeholder Engagement and Knowledge... Closed Oct 01, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #629: WP4 - VREs Deployment and Operation [Months: 1-30] Closed Aug 03, 2015 Mar 30, 2018
Related to BlueBRIDGE - Project WP #641: WP5 - Supporting Blue Assessment: VREs Development [Month... Closed Oct 09, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #654: WP6 - Supporting Blue Economy: VREs Development [Months: ... Closed Oct 01, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #665: WP7 - Supporting Blue Environment: VREs Development [Mont... Closed Mar 01, 2016 Apr 26, 2018
Related to BlueBRIDGE - Project WP #677: WP8 - Support Blue Skills: VREs Development [Months: 1-30] Closed Sep 01, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #686: WP9 - VRE Commons Development [Months: 1-30] Closed Oct 15, 2015 Jan 18, 2018
Related to BlueBRIDGE - Project WP #697: WP10 - Interfacing Infrastructures [Months: 1-30] Closed Mar 07, 2016 Jun 01, 2017

History

#1 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #591: WP1 - Project Management [Months: 1-30] added

#2 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #602: WP2 - Project Governance, Exploitation and Sustainability [Months: 1-30] added

#3 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #612: WP3 - Communication, Stakeholder Engagement and Knowledge transfer [Months: 1-30] added

#4 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #629: WP4 - VREs Deployment and Operation [Months: 1-30] added

#5 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #641: WP5 - Supporting Blue Assessment: VREs Development [Months: 1-30] added

#6 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #654: WP6 - Supporting Blue Economy: VREs Development [Months: 1-30] added

#7 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #665: WP7 - Supporting Blue Environment: VREs Development [Months: 7-30] added

#8 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #677: WP8 - Support Blue Skills: VREs Development [Months: 1-30] added

#9 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #686: WP9 - VRE Commons Development [Months: 1-30] added

#10 Updated by Pasquale Pagano about 4 years ago

  • Related to Project WP #697: WP10 - Interfacing Infrastructures [Months: 1-30] added

#11 Updated by Pasquale Pagano about 4 years ago

  • Assignee set to Leonardo Candela

#12 Updated by Leonardo Candela over 3 years ago

  • Risk Probability Rank changed from Very Low to High
  • Priority changed from Normal to High
  • Status changed from New to In Progress

We are accumulating some delays in submitting / finalising project deliverables. This is mainly affecting the final submission to the EC via the PP. Part of the delay is due to the multi-step workflow characterising the deliverable production.

The QAO is actively monitoring deliverables production process and is reinforcing the alerting mechanism by sending remainders to the Deliverable Editor and Reviewer.

#13 Updated by Leonardo Candela over 3 years ago

  • Risk Materialized changed from No to Yes

#14 Updated by Leonardo Candela over 3 years ago

  • Applied Mitigation changed from No to Yes

#15 Updated by Leonardo Candela over 1 year ago

  • Status changed from In Progress to Closed