Project WP #629

WP4 - VREs Deployment and Operation [Months: 1-30]

Added by Franco Zoppi almost 4 years ago. Updated about 1 month ago.

Status:ClosedStart date:Aug 03, 2015
Priority:UrgentDue date:Mar 30, 2018
Assignee:Paolo Fabriani% Done:

100%

Sprint:WP04
Lead beneficiary:3 - ENG Budget Effort (PM):65.00
Milestones:
Duration: 695

Description

Objectives
This Work Package develops and operates the set of planned VREs and the new ones that will be identified and developed during the Project. To achieve this objective, it uses the services provided by the European data and computing infrastructures and by tools, facilities, and services provided by the organizations supporting the different VREs. In particular, the Work Package will deploy and operate 9 Virtual Research Environments by using WP5-WP8 outcomes.
The entire stack of facilities, from the storage and computing level to the data and application level, is made accessible via a coherent, easy-to-exploit, and policy-based framework that hides the complexities inherent in distributed networks of resources. The operation of the VREs is based on the procedures and integrated tools largely tested and used by D4Science in the last five years. Such procedures and tools, when empowered with the technologies developed in WP9 and WP10, will allow operating the VREs from the first month of the Project. This Work Package is also in charge of managing the software release process covering all stages (building, documentation, validation, distribution).

Description of work and role of partners
ENG, CNR, UOA, CITE


Subtasks

Project Task #630: T4.1 BlueBRIDGE Infrastructure Operation [Months: 1-30]ClosedDaniele Pavia

D4Science Infrastructure - Task #3181: Update RStudio on rstudio.d4science.orgClosed_InfraScience Systems Engineer

gCube - Feature #1405: Enable Federated login on services and iMarine GatewaysClosedMassimiliano Assante

Project Activity #1441: Integrate .Net algorithms on the BlueBRIDGE computing pla...RejectedPaolo Fabriani

Task #1461: Design the interface between the Statistical Manager and EwEClosedJeroen Steenbeek

Task #4924: Connect EwE desktop software to the BB cloud for running ...RejectedPaolo Fabriani

Task #4939: The authorization service has to return the email of the ...RejectedLucio Lelii

Task #1367: Pre-production infrastructure creationRejectedPaolo Fabriani

D4Science Infrastructure - Task #451: New VO creation for preproductionRejectedRoberto Cirillo

D4Science Infrastructure - Task #450: Dismiss Ecosystem VO and related servicesClosedRoberto Cirillo

D4Science Infrastructure - Task #449: New root VO creation for pre productionClosedDaniele Pavia

D4Science Infrastructure - Task #1795: new test portal @ENGClosedDaniele Pavia

Project Task #631: T4.2 VREs Creation and Deployment [Months: 1-30]ClosedMassimiliano Assante

Task #2111: Stock Assessment VRE: extensions to supportClosedMassimiliano Assante

Task #4217: Tuna Atlas VRE: extensions to supportClosedMassimiliano Assante

VRE #4846: VRE Creation for ICCAT BFT-EReleasedRoberto Cirillo

D4Science Infrastructure - Support #4977: publishing the "parallelized_STEP1_VPA_ICCAT_BFT_E_Retros...ClosedTAHA IMZILEN

D4Science Infrastructure - Support #4998: publishing the "Step_4_Vpa_Iccat_Bft_E_Report" algorithm ...ClosedGianpaolo Coro

Project Activity #5087: Develop a logo for ICCAT BFT VREClosedJulien Barde

Support #5113: packages uninstalledClosedAndrea Dell'Amico

Task #9673: Create a VRE for FlyBy SMEClosedMassimiliano Assante

VRE #9674: Create a VRE for the Sinay SMEReleasedGianpaolo Coro

Project Task #632: T4.3 VREs Operation [Months: 1-30]ClosedRoberto Cirillo

Task #7540: Provide every VRE with the Resource CatalogueRejectedPasquale Pagano

Project Task #633: T4.4 Software integration and release [Months: 1-29]ClosedMaria Di Girolamo

gCube - Feature #948: test how to model gCube software in JenkinsClosedMaria Di Girolamo

Task #3922: Migration to GitClosedGabriele Giammatteo

Task #3923: publish gCube code on ZenodoClosedGabriele Giammatteo

Project Activity #6681: Distribution of gCube software in Docker containersClosedGabriele Giammatteo

gCube - Support #7134: org.gcube.resource-managementClosedLuca Frosini

gCube - Support #7582: Creation of Master Ticket for Release 4.4.0 - 4.4.0 gCore...ClosedLuca Frosini

gCube - Task #8179: Creation of Master Ticket for Release 4.5.0 - 4.5.0 gCore...ClosedLuca Frosini

gCube - Task #8232: Produce Release Notes for gCube 4.4.0ClosedNikolas Laskaris

D4Science Infrastructure - Task #8257: Please produce release notes for gCube 4.4.0ClosedNikolas Laskaris

gCube - Task #8816: Creation of Master Ticket for Release 4.6.0 - 4.6.0 gCore...ClosedLuca Frosini

Project Activity #9371: Zenodo Publisher - Support for VersioningClosedGabriele Giammatteo

gCube - Task #9663: Produce Release Notes for gCube 4.6.1ClosedNikolas Laskaris

gCube - Task #9898: Produce Release Notes for gCube 4.7.0ClosedNikolas Laskaris

gCube - Task #7081: Produce Release Notes for gCube 4.2.1ClosedNikolas Laskaris

gCube - Task #8813: Produce Release Notes for gCube 4.5.0ClosedNikolas Laskaris

gCube - Task #9388: Produce Release Notes for gCube 4.6.0ClosedNikolas Laskaris

gCube - Task #3245: Release Notes for gCube 3.10.1ClosedNikolas Laskaris

gCube - Task #2172: Release Notes for gCube 3.10.0ClosedNikolas Laskaris

gCube - Task #9969: Produce Release Notes for gCube 4.7.1ClosedNikolas Laskaris

gCube - Task #10342: Produce Release Notes for gCube 4.8.0ClosedNikolas Laskaris

gCube - Task #10641: Produce Release Notes for gCube 4.9.0ClosedNikolas Laskaris

gCube - Task #11060: Creation of actual testing plan for the portlet org.gcube...ClosedKonstantinos Apostolopoulos

gCube - Task #11103: Produce Release Notes for gCube 4.10.0ClosedNikolas Laskaris

gCube - Task #11521: Produce Release Notes for gCube 4.11.0ClosedMaria Di Girolamo

gCube - Task #12646: Produce Release Notes for gCube 4.12.1ClosedMaria Di Girolamo

gCube - Task #12645: Produce Release Notes for gCube 4.12.0ClosedMaria Di Girolamo

gCube - Task #12907: Produce Release Notes for gCube 4.13.0ClosedMaria Di Girolamo

gCube - Task #16131: Produce Release Notes for gCube 4.13.1ClosedMaria Di Girolamo

gCube - Task #16679: Produce Release Notes for gCube 4.14-0ClosedMaria Di Girolamo

gCube - Feature #3896: Give VRE Managers options to manage new requestsClosedMassimiliano Assante

D4Science Infrastructure - Task #3894: Create service endpoint resource for SimulFishGrowth DBClosedMassimiliano Assante

Task #3893: Create a database for SimulFishGrowth (WP6)ClosedTommaso Piccioli

Project Activity #4530: Additional functionnalities for RStudio within VREsClosedLucio Lelii

Project Activity #4281: Check the feasibility of user's requirementsClosedGianpaolo Coro


Related issues

Related to BlueBRIDGE - Key Performance Indicator #974: Blue Commons: Number of software releases Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Key Performance Indicator #975: Blue Commons: Number of resolved ticket request Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Key Performance Indicator #976: Blue Commons: Time to close a ticket request Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Risk #977: 1. Misalignment of user requirements with perceived speci... Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Risk #982: 6. A partner / body underperforms, defaults or faces othe... Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Risk #983: 7. Domain or project’s concepts become obsolete or irrele... Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Risk #984: 8. Delays in production of deliverables, be it interim on... Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Risk #986: 10. Lack of required competences for the completion of pr... Closed Oct 12, 2015 Feb 28, 2018
Related to BlueBRIDGE - Task #1340: Move CITE's OpenSource code into a separate publicly acce... Closed Nov 11, 2015 Jan 20, 2016

History

#1 Updated by Franco Zoppi almost 4 years ago

  • Start date changed from Sep 11, 2015 to Sep 01, 2015

due to changes in a related task

#2 Updated by Franco Zoppi almost 4 years ago

  • Status changed from New to In Progress

#3 Updated by Massimiliano Assante almost 4 years ago

  • Assignee set to Gabriele Giammatteo

#4 Updated by Massimiliano Assante almost 4 years ago

  • Assignee changed from Gabriele Giammatteo to Paolo Fabriani

#5 Updated by Gabriele Giammatteo over 3 years ago

KO meeting
During the KickOff meeting:
* the Work Package structure and activities have been presented
* the tools SVN, ETICS, BTRT, Distribution Site have been presented
* a new release procedure with major changes in the usage of the ticketing system has been presented. Some discussions started, but they will be finalized off-line during the first month of the project. Once agreed on a final version of the procedure, it will be tested and then replace the current one

September 2015 Activities
In WP4 the milestone MS3 has been achieved by deploying the BlueBRIDGE Gateway to host all the VREs of the project.

In task T4.2 a total of 10 VREs have been created with tools to support the reporting, communication and coordination activities in BlueBRIDGE: BlueBRIDGEProject, AquacultureAtlasGeneration, PerformanceEvaluationInAquaculture, ProtectedAreaImpactMaps, StockAssessment, StocksAndFisheriesKB, StrategicInvestmentAnalysis, KnowledgeBridging, BlueCommons, BlueUptake

In task T4.3 the VREs have been operated. A total of 59 tickets have been created, 42 tickets have been managed, 31 tickets have been closed. Relevant, in this phase, wa the management of the user registration to the VREs: a total of 210 users in 10 VREs.

In task T4.4 some tools updated and/or configured: Redmine (CNR), new Distribution Site (CNR), ETICS (ENG). Integration of gCube 3.9.0 started (ALL)
* New release procedure defined and being tested in gCube 3.9.0 - 101 components released - (ENG, CNR)
* Update of the Integration and Distribution Wiki to reflect new procedures and tools (CNR, ENG)
* Jenkins evaluation started. An instance deployed @ENG and initial tests carried out. To be continued in next months (ENG)

Next six months planned activities
In addition to the routine activities of operation of the D4Science infrastructure (T4.1), management of VREs (T4.2-3) and integration software releases (T4.4), the activities already planned for the next six months are:
* set-up of a separate infrastructure to host testing and preproduction environments
* discuss and agree on a shared procedure to support the exploitation of existing VREs and resources;
* discuss and agree on a shared procedure to support training on existing VREs and resources;
* create a BlueBRIDGE Gateway explicitly dedicated to host the “BlueBRIDGE” VREs;
* create a Wiki page summarising the procedures characterising VREs Creation and Deployment;
* rethink documentation review procedure (in iMarine it has not been effective)
* replace BTRT builds with ETICS remote builds (starting from org.gcube.HEAD) as much as possible
* carry out tests with Jenkins to understand how to use it in gCube release process
* migration to Git. Set-up repositories, update integration procedures and tools
* by M5 GitHub to be used to publish source code after releases

More activities will be discussed and defined during the next f2f meeting in Athens.

#6 Updated by Pasquale Pagano over 3 years ago

#7 Updated by Pasquale Pagano over 3 years ago

#8 Updated by Pasquale Pagano over 3 years ago

#9 Updated by Pasquale Pagano over 3 years ago

  • Related to Risk #977: 1. Misalignment of user requirements with perceived specifications added

#10 Updated by Pasquale Pagano over 3 years ago

  • Related to Risk #982: 6. A partner / body underperforms, defaults or faces other severe operation issues added

#11 Updated by Pasquale Pagano over 3 years ago

  • Related to Risk #983: 7. Domain or project’s concepts become obsolete or irrelevant during project’s lifetime added

#12 Updated by Pasquale Pagano over 3 years ago

  • Related to Risk #984: 8. Delays in production of deliverables, be it interim ones (with dependencies) or final ones added

#13 Updated by Pasquale Pagano over 3 years ago

  • Related to Risk #986: 10. Lack of required competences for the completion of project’s tasks added

#14 Updated by Gabriele Giammatteo over 3 years ago

October 2015 Activities
* the new preproduction infrastructure has been designed. Deployment of the services started and will continue in November
* CouchDB clusters (production, preproduction, development) in High Availability have been deployed and used by Accounting, Authorization, SmartExecutor
* a new VRE dedicated to PSC members (9 people) has been setup and used during meetings
* 29 new users have been registered to the BlueBRIDGE VREs
* in the context of VRE operation 65 tickets have been created, 50 tickets have been managed, 38 tickets have been closed
* release gCube 3.9.0 has been integrated with 133 components added/updated in 17 different subsystem.
* release Procedure and Documentation procedures have been updated to fit the new tools and needs of BlueBRIDGE project. Tools (Redmine, ETICS) and documentation (gCube wiki) have been updated accordingly.
* Deliverable D4.1 based on the gCube wiki has been reviewed and delivered to the commission.
* A Jenkins instance has been configured at ENG infrastructure and preliminary tests carried out

#15 Updated by Paolo Fabriani over 3 years ago

#16 Updated by Paolo Fabriani over 3 years ago

#17 Updated by Gabriele Giammatteo over 3 years ago

November 2015 Activities

  • gCube 3.9.0 has been released (in total 134 new/updated components). The release has been deployed first in pre-production for testing and then in the production infrastructure
  • the root VO of the pre-production infrastructure has been deployed accordingly with the decisions taken at Athens f2f meeting. This activity is still in progress and will be completed during next reporting period
  • in the context of VREs operation: 6 new users have been registered to the BlueBRIDGE VREs, 74 tickets have been created, 41 tickets have been managed and 22 tickets have been closed
  • a new procedure for portlet functional test has been defined. The required templates to describe and execute tests have been produced. A request to developers to provide functional tests for their portlet has been sent
  • A new build server has been provided by CNR to build org.gcube.HEAD. The daily builds of gCube HEAD appear in BTRT
  • new fields for reporting documentation status of released components has been added to release tickets
  • KPIs about number of requests managed using Redmine has been calculated (#974, #975, #976): from beginning of the project, a total of 127 requests have been managed with an average time to process the request of 12 days.
  • Milestone MS05 has been achieved "BlueBridge VREs planning and procedures"

#18 Updated by Gabriele Giammatteo over 3 years ago

December 2015 Activities

In Task T4.1:

  • the configuration of pre-production infrastructure continued. The activity could not be finished in December because of network issues ENG-side that needs to be solved in order to make the infrastructure available to the consortium

In Task T4.2:

  • a new VREs has been created: Training Course in the R Environment (TCRE). It will be used by ICES to support their courses (#1676)

In Task T4.3:

  • 17 new users have been registered to BlueBRIDGE VREs
  • 32 requests concerning VREs operation have been successfully managed

In Task T4.4:

  • integration of gCube 3.10.0 continued with regular builds every day
  • clean-up and re-factor of gCube components continued with the objective of removing obsolete components. In December a total of 42 components have been removed from release gCube 3.10.0
  • modifications to the build/release tools have been updated to generate Maven artifacts that include svn revision number in the file name. However, the new versioning system will be used in gCube 3.11.0
  • All partners contributed to specify portlet functional tests. They are available in the public workspace of iMarine portal (https://goo.gl/F0fNFX). Tests have been specified for 18 portlets out of 26

#19 Updated by Massimiliano Assante over 3 years ago

  • Related to Task #1340: Move CITE's OpenSource code into a separate publicly accessible repository added

#20 Updated by Gabriele Giammatteo over 3 years ago

January 2016 Activities

For the VREs operation:

  • 16 new users have been registered to the BlueBRIDGE VREs
  • 26 tickets have been created, 49 tickets have been managed, 39 tickets have been closed

For the gCube integration:

  • Integration of release gCube 3.10.0 continued during January
  • Alternative solutions to publish artifacts on GitHub.com and to strategies to migrate to Git have been investigated and presented at the 1st TCOM

#21 Updated by Gabriele Giammatteo over 3 years ago

Feb 2016 Activities

Concerning the operation of D4Science Infrastructure:

  • upgrade of the infrastructure with gCube 3.10.1 to solve urgent issues with logging in production
  • problems with the ROOT VO of the new pre-production infrastructure have been fixed.

Concerning the operation of VREs:

  • 36 new users have been registered to the BlueBRIDGE VREs
  • 92 tickets have been created, 64 tickets have been managed, 41 tickets have been closed

Concerning the release of gCube software:

  • a maintenance release started (org.gcube.3.10.0-1) to fix a bug in logs configuration.
  • release gCube 3.10.0 has been closed and published on gCube website
  • the process for the publication of released source code on GitHub has been set-up
  • activity to evaluate if and how it is possible to generate the fullgar of Ant components started
  • definition of a procedure to update the README and LICENSE files of all gCube components started
  • Work started on gCube 3.11.0. In this release components will split in two separate releases: gCore-dependant and SmartGears-dependant components. An initial division has been done and a list of components to move has been produced.

#22 Updated by Gabriele Giammatteo about 3 years ago

Mar 2016 Activities

In T4.1 for the operation of D4Science infrastructure:
- the production infrastructure has been updated to gCube 3.10.1
- no relevant activities have been performed during this period on the testing infrastructure other than maintenance activities.

In T4.3 for the operation of VREs:
- 11 users have been registered to the BlueBRIDGE VREs
- 36 users have been registered to the BlueBRIDGE VLAB
- 41 tickets have been created, 49 tickets have been managed, 47 tickets have been closed;

In T4.4 for the release of gCube software:
- distro (README, LICENSE, INSTALL, ...) files of all components have been updated in gCube 3.10.1 by technical partners accordingly to a new format defined and documented on the wiki
- During the integration of gCube 3.10.1, a mechanism to automatically generate in ETICS source packages for all components has been developed (they will be used for the publication of the releases on GitHub)
- integration of gCube 3.10.1 continued for the entire month to allow update of distro files
- integration of gCube 3.11.0 started. Since this release, gCore-based and SmartGears-based components will be released separately. This needed an extra-effort to "divide" the components in two separate releases analysing the dependencies

#23 Updated by Gabriele Giammatteo about 3 years ago

  • Start date changed from Sep 01, 2015 to Aug 03, 2015

due to changes in a related task

#24 Updated by Gabriele Giammatteo about 3 years ago

Apr 2016 Activities

In T4.1:
- the D4Science infrastructure started to be upgraded with new artifacts released in gCube 3.11.0

In T4.3:
- in the last month 74 users have been registered to the BlueBRIDGE VLAB and the new VLAB "ICES_TCSSM" has been created
- tickets reporting on issues and pertaining to VREs Operation have been managed: 38 tickets have been created, 18 tickets have been managed, 34 tickets have been closed;

In T4.4:
- integration of gCube 3.11.0 and gCube 3.11.0-gcore releases continued during April.
- identification and (when possible) re-factoring of gCore based components has been performed. Components not refactored has been moved in gCube 3.11.0-gcore
- during the integration of these releases the updating of the README and LICENSE files continued.

#25 Updated by Gabriele Giammatteo about 3 years ago

May 2016 Activities

In T4.1:

  • upgrade of preproduction infrastructures started to allow testing of gCube 3.11.0.
  • deployment plan for gCube 3.11.0 in the production infrastructure has been produced. The upgrade of the production is planned for June the 1st

In T4.2:

  • a new VRE for supporting ICES training courses was deployed in May. It is intended to serve the course titled "Social Science Methods for Natural Scientists"

In T4.3:

  • A total of 74 new users have been registered to the BlueBRIDGE VLABs: Bionym (20), Biodiversity Lab (26), FAO Tuna Atlas (1), Scalable Data Mining(3), Tabular Data Lab (18), ICES_TCSSM (6)

In T4.4:

  • Release gCube 3.11.0 has been integrated and released at the end of May. This release was split in two different projects (for integration purposes):
    • org.gcube.3.11.0: 234 components updated (14 new + 73 upd + 147 drp) on 24 subsystems;
    • org.gcube.3.11.0-gcore: 329 components updated (3 new + 28 upd + 298 drp) on 20 subsystems;

#26 Updated by Gabriele Giammatteo almost 3 years ago

June 2016 Activities

In T4.1
- gCube 3.11 release has been deployed on D4Scienece production infrastructure
- prepartion of development and preproduction infrastructures started. This activity will continue during next month during the integration of gCube 4 release

In T4.2:
The VRE Plan report has been updated and the related tickets re-organised to better organize the activity for the delivery of the VREs. According to this reorganization, the following VREs are planned in the short term:
- 3 new VREs are planned to be release at the beginning of September for Blue Skills
- 7 new VREs are planned to be released in October for Blue Assessment and Blue Economy

In T4.3:
-8 new users have been registered to the BlueBRIDGE VREs (342 users in total)
-16 new users have been registered to the BlueBRIDGE VLABs (735 users in total)
- tickets reporting on issues and pertaining to VREs Operation have been managed: 54 tickets have been created, 18 tickets have been managed, 36 tickets have been closed;

In T4.4
- integration of gCube 4 release started in the last half of the month
- org.gcube.HEAD release has been split in org.gcube.HEAD and org.gcube.HEAD-gcore as already done for gCube 3.11
- the functional testing procedure and test plans have been reviewed and updated
- activities on migration to Git and publication of artifacts on Zenodo continued and interim results have been presented at the BlueBRIDGE 2nd TCOM

Finally, work package partners worked at the preparation of material for BlueCommons sessions of the2nd BlueBRIDGE TCOM

#27 Updated by Gabriele Giammatteo almost 3 years ago

July/August 2016 Activity

In T4.1
- preproduction infrasturcture has been upgraded to gCube 4.0.0 during the integration of the release to perform the deployment and functional tests
- production infrasturcture has been upgraded to gCube 4.0.0 after the release was closed

In T4.2
- New VRE for ICCAT BFT-E has been created
- VREs for two ICES training courses have been created: "Data Limited Stock Assessment" and "Design and analysis of statistically sound catch sampling programmes"

In T4.3
- In the last 2 months 7 users have been registered to the BlueBRIDGE VREs: AquacultureAtlasGeneration(1), ProtectedAreaImpactMaps (1), StockAssessment(4), StocksAndFisheriesKB(1). A total of 342 users are registered to BlueBRIDGE VREs.
- In the last 2 months 19 users have been registered to the BlueBRIDGE VLAB: BiOnym(3), BOBLME_HilsaAWG(2), FAO_TunaAtlas(3), ICES_DALSA(3), ICES_DASC(4), ICES_MSE(2), ICCAT_BFT-E(2). A total of 754 users are registered to BlueBRIDGE VLabs.
- Tickets reporting on issues and pertaining to VREs Operation have been managed: 26 tickets have been created, 49 tickets have been managed, 68 tickets have been closed;

In T4.4
- gCube 4.0.0 release has been integrated, tested and deployed during July. The release included 40 new component and 134 updated components. This release included a major upgrade of the portal technology at Liferay 6.2. All portlets have been migrated to the new version. Technical partners CNR, ENG, UoA carried out functioanl testing of portlets.
- Git migration and Zenodo publication activities progressed but still ongoing.
- ETICS received an update to reduce the effort needed for developers to keep ETICS updated with changes in the pom.xml.

#28 Updated by Gabriele Giammatteo over 2 years ago

September 2016 Activity

In T4.1
- ENG worked to update its testing infrastructure to keep it aligned with gCube releases to be able to support functional testing of some portlets in future releases (https://support.d4science.org/issues/629);

In T4.2
- RStudioLab VRE was created in gCubeApps VO. It is conceived as a development environment for R. It includes an RStudio instance and it is integrated with social networking facilities as well as with the workspace enabling VRE members to put in place collaborative working practices;
- RPrototypingLab VRE was created in gCubeApps VO. It provides an environment powered by RStudio (an open source development environment including a code editor, debugging and visualisation tools), gCube data analytics platform and social networking facilities and a shared workspace;
- GRSF VRE (VLab) was created under the FARM VO. The main purpose of this VRE is to provide scientists with an environment and the tools for accessing stocks and fisheries information;

In T4.3
A total of 369 users have been registered to the BlueBridge VREs.
In particular in the last month, 27 users have been registered to the BlueBRIDGE VREs:
AquacultureAtlasGeneration(1), BlueBRIDGEProject(6), BlueCommons(2), BlueUptake(1), KnowledgeBridging(1), PerformanceEvaluationInAquaculture(1), ProtectedAreaImpactMaps (1), StockAssessment(9), StocksAndFisheriesKB(4), StrategicInvestmentAnalysis(1).

A total of 861 users have been registered to the BlueBridge VLAB.
In particular, in the last month 117 users have been registered to the BlueBRIDGE VLAB :
BiOnym(3), BiodiversityLab(10), FAO_TunaAtlas(2), ScalableDataMining(3), TabularDataLab(2), VME-DB(-1), ICES_DALSA(25), ICES_DASC(15), ICCAT_BFT-E(19), RPrototypingLab(20), RStudioLab(15), GRSF(4)

Tickets reporting on issues and pertaining to VREs Operation have been managed: 70 tickets have been created, 86 tickets have been managed, 51 tickets have been closed;

In T4.4
- preparation of gCube 4.1.0 release started (org.gcube.4.1.0: https://support.d4science.org/issues/2372; org.gcube.4.1.0-gcore:https://support.d4science.org/issues/4976): nightly builds have been activated and monitored and functional testing procedure has been setup ;
Main changes in this release are: Authorization 2.0, SmartGears 2.0, new GeoAnalytics and InvestmentAnalysis subsystems. This release integration and testing will continue and completed during October 2016;
- for Zenodo publication activity, the model and the format for metadata has been decided. The same metadata will be published also in the Data Catalogue (#5114);
- distribution Wiki has been updated to reflect changes in testing procedures (https://support.d4science.org/issues/1431);
- editing of deliverable D4.2 started (https://support.d4science.org/issues/635);

#29 Updated by Gabriele Giammatteo over 2 years ago

October '16 Activity Report

In T4.1

  • preprod infrastructure upgraded with gCube 4.1 at the beginning of the month to let testers carry out functional portlet tests;
  • production infrastructure upgraded to gCube 4.1 release at the end of the month;

In T4.2

  • the Stock Assessment Advanced VRE has been created to support the ICES' Stock Assessment Advcanced training course going to be held on 28th of November to 2 December in ICES HQ, Copenhagen, Denmark;
  • the ICES_FIACO VRE has been created to support the ICES' "Principles and methods of broadband/wideband technologies: application to fisheries acoustics", going to be held on 8 – 12 December 2016 , Bergen, Norway;

In T4.3

  • 10 users have been registered to the BlueBRIDGE VREs (379 total users): AquacultureAtlasGeneration(2), BlueBRIDGEProject(2), ProtectedAreaImpactMaps(3), StockAssessment(1), StocksAndFisheriesKB(1), StrategicInvestmentAnalysis(1);
  • 40 users have been registered to the BlueBRIDGE VLAB (905 total users): BiOnym(1), BiodiversityLab(9), BOBLME_HilsaAWG(1), FAO_TunaAtlas(1), ScalableDataMining(2), TabularDataLab(3), ICCAT_BFT-E(3), RPrototypingLab(4), RStudioLab(1), GRSF(1), ICES_FIACO(9), ICES_StockAssessmentAdvanced (5);
  • tickets reporting on issues and pertaining to VREs Operation have been managed: 45 tickets have been created, 53 tickets have been managed, 41 tickets have been closed;

In T4.4

  • integration, testing and roll-out of gCube 4.1.0. The release has been finalized and the production infrastructure upgraded at the end of the month. The release involved, 46 new components, 170 updated components and 2 new subsystems: investment-analysis and geoanalytics;
  • production of D4.2 on the BlueBRIDGE wiki. Most of the content is available, but it is not yet finalized.

D4.2 is in delay of few days (expected by Oct 31th), it will be ready by November the 11th;

#30 Updated by Gabriele Giammatteo over 2 years ago

November 2016 Activity

In T4.1

  • executed upgrade of components released with gCube 4.1.1;
  • started development on ansible roles to automate testing infrastructure deployment. Begun testing these new roles by the end of the month;

In T4.2

6 new VREs have been deployed in this month:

  • Alieia VRE: provides the Alieia's aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis;
  • Forkys VRE: provides the Forky's aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis;
  • EllinikaPsaria VRE: provides the EllinikaPsaria's aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis;
  • SIASPA VRE: offers a geospatial multi-factor optimization and alerting platform for intelligent identification of locations of interest for investors and stakeholders seeking optimization of intended investments and scientists seeking areas that are becoming of environmental importance;
  • AquacultureTrainingLab VRE: provides its users with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis;
  • GRSF_Admin VRE: provides Global Record of Stock and Fisheries (GSRF) editors with an environment and the tools for accessing stocks and fisheries records, validate them, and approve. When approved, the records will become available in the GSRF VRE;

In T4.3

  • 4 new users in the BlueBridge VREs: AquacultureAtlasGeneration(1), BlueUptake(1), StockAssessment(2).
  • 186 new users have been registered to the BlueBRIDGE VLAB: AquacultureTrainingLab(33), BiodiversityLab(4), ICCAT_BFT-E(7), ICES_FIACO(20), ICES_StockAssessmentAdvanced(22), iSearch(51), RPrototypingLab(13), RStudioLab(11), ScalableDataMining(1), SIASPA(6), TabularDataLab(1), VME-DB(3), WECAFC-FIRMS(20)
  • tickets reporting on issues and pertaining to VREs Operation have been managed: 49 tickets have been created, 65 tickets have been managed, 59 tickets have been closed;

In T4.4

  • gCube 4.1.1 maintenance release rolled-out to fix a critical issue in production;
  • integration of gCube 4.2.0 started at the end of the month;
  • deliverable D4.2 finalized (#635; https://goo.gl/Gi0sgy);
  • Zenodo Publisher completed (#3923);

#31 Updated by Gabriele Giammatteo over 2 years ago

December 2016 and January 2017 Activity

In T4.1
- migration of development infrastructure to Java 8 started. Status and issues are being traced in #6306
- upgrade of the preprod and production infrastructures to gCube 4.2

In T4.2

  • A new Virtual Organisation named D4Research was created in December to better support the growing need of hosting VREs and VLABs in the infrastructure. Some VREs deployed under gCubeApps VO have been moved to D4Research VO to better distribute the workload (#6450)
  • On December 15th AnalyticsLab VRE (VLab) was created under the D4Research Virtual Organisation. This VLab is intended to be a demonstrative environment making available the methods the infrastructure can offer for data analytics
  • On December 20th BlueBRIDGEReview VRE was created under the D4Research Virtual Organisation. This VRE was conceived to support the BlueBRIDGE Project Review and to enable Commission with the assistance of independent experts to have access to a working environment supporting their assessment exercise.
  • On January 8th ICES_MSY VRE (VLab) was created under the D4Research Virtual Organisation. This VRE was conceived to support the ICES Training course on methods for setting proxy MSY reference points, held in 25th and 26th January 2017 Copenhagen, Denmark.

In T4.3

  • 23 new VRE users registered: AquacultureAtlasGeneration(1), BlueBRIDGE-EAB(1), BlueCommons(3), BlueUptake(1), Knowledge Bridging(3), Performance Evaluation in Aquaculture(3), Protected Area Impact Maps(1), StockAssessment(4), Stocks & Fisheries Knowledge Base(2), Strategic Investment Analysis(4)
  • 201 new VLab users: Alieia VRE(3), AnalyticsLab(15), AquacultureTrainingLab(26), BiodiversityLab(6), Bionym(7), BlueBRIDGEReview(14), Ellinika Psaria VRE(1), FAO Tuna Atlas(1), GRSF(8), GRSF Admin(13), ICCAT_BFT-E(1), ICES_MSY(55), RStudio Lab(13),Scalable Data Mining(7), SIASPA(5), TabularDataLaB(3), VME-DB(3), WECAFC-FIRMS(20)
  • tickets reporting on issues and pertaining to VREs Operation have been managed: 54 tickets have been created, 63 tickets have been managed, 60 tickets have been closed;

In T4.4
- gCube4.2.0 ( #5058 and #5060) has been closed: . In total 121 components have been updated/added to the release and the integration of the release took 19 days.
- Modified the root-workaspace for the TestPlan: gCube and not BlueCommons: https://goo.gl/bRtrI0. In this way all developers and testers can access it. 39 portlets pass the test: https://wiki.gcube-system.org/gcube/FTMasterTablegCube4.2.0.
- review and modifications to the release and testing procedures
- release gCube 4.3 started

In addition:
- Deliverable D4.1 resubmitted
- D4.2 and D4.3 finalized and submitted
- preparation of 1st review meeting

#32 Updated by Gabriele Giammatteo over 2 years ago

February 2017 Activity

In T4.1

  • upgrade of production with gCube 4.2.1
  • upgrade of pre-production with gCube 4.3.0
  • Java 8 Migration
  • further work on gCube enabling infrastructure automated deployment with ansible for our gCube testing infrastructure @ENG

In T4.2

  • DRuMFISH VRE created. This Virtual Research Environment is conceived for a WP8 course to be held on 21-23 March 2017 in Lorient (FR)

In T4.3

  • 3 new users to VREs: BlueBRIDGE Project (2), Protected Area Impact Maps(1)
  • 44 new users to VLabs: AnalyticsLab(2), AquacultureTrainingLab(1), BiodiversityLab(2), BlueBRIDGEReview(1), GRSF(2), GRSF Admin(1), ICES_MSY(26), RPrototypingLab(3), Scalable Data Mining(3), DRuMFISH (4)
  • managed support requests: 36 tickets have been created, 47 tickets have been managed, 46 tickets have been closed;

In T4.4

  • gCube 4.2.1 maintenance release integrated and delivered. It tooks 8 days in total and fixed few issues on portal components and the data catalogue
  • new testing procedure reviewed to improve the activities of the developers and tester. Redmine will replace Excel and Wiki tables to organize the procedure (#7063)
  • upgrade of Wiki to reflect changes in the procedures
  • gCube 4.3.0 integration phase finalized. Tests will start on March

#33 Updated by Leonardo Candela over 2 years ago

  • Due date changed from Feb 28, 2018 to Mar 16, 2017

due to changes in a related task

#34 Updated by Maria Di Girolamo over 2 years ago

  • Due date changed from Oct 31, 2016 to Apr 02, 2017

due to changes in a related task

#35 Updated by Maria Di Girolamo over 2 years ago

  • Due date changed from Apr 02, 2017 to Mar 16, 2017

due to changes in a related task

#36 Updated by Gabriele Giammatteo about 2 years ago

March 2017 Activity

In T4.1

  • gCube 4.3.0 deployed on production
  • gcore ansible roles finalised. Able to deploy a whole working gcore infrastructure (GHN and enabling services) plus a root VO and a portal instance from scratch in a matter of minute
    • next step will be to integrate this in the gCUbe build and testing pipeline
  • working on smartgears containerization: developed a basic ansible role that creates and instances a smartgears docker container

In T4.2

  • InfraTraining VRE was created under the D4Research Virtual Organisation. The VLab is planned to be used by students and other partners from UoA, or other organisations

In T4.3

  • 5 new users to VREs: BlueBRIDGE-EAB (1), BlueBRIDGE Project (1), Stock Assessment(3)
  • 101 new users to VLABs: AnalyticsLab(15), AquacultureTrainingLab(4), BiodiversityLab(12), Bionym (11), DRuMFISH(24), FAO Tuna Atlas(2), GRSF(-2), GRSF Admin(2), ICCAT_BFT-E(3), ICES_MSY(4), InfraTraining (5), RStudioLab(8), Scalable Data Mining(5), SIASPA(1), Tabular Data Lab(2)
  • tickets reporting on issues and pertaining to VREs Operation have been managed: 65 tickets have been created, 65 tickets have been managed, 64 tickets have been closed;

In T4.4

  • release procedure has been re-discussed and improved. The main new characteristics are: components split in three groups (enabling, common, community) and released, tested and deployed in different moments; fixed release windows; no pauses between releases;
  • gCube 4.4.0 started on March (it will be closed on Apr 30);
  • Several obsolete components have been removed from gCube 4.4.0 (about 100), allowing faster builds;
  • Redmine tool updated to implement novelties to the release and functional test procedures;
  • ETICS Portal updated with the possibility to hide obsolete modules;

Preparation and participation to the 4th TCOM

#37 Updated by Maria Di Girolamo about 2 years ago

  • Due date changed from Oct 31, 2016 to May 02, 2017

due to changes in a related task

#38 Updated by Gabriele Giammatteo about 2 years ago

April 2017 Activity

In T4.1

  • migration to Java 8 of Development infrastructure completed
  • preprod and production infrastructures upgraded with gCube 4.4.0
  • Ansible roles for gCore and Smartgears Container updated
    • ENG roles have been published and are being merged with the ones in use at CNR infrastructure

In T4.2

  • Introduction to Stock Assessment (ICES_IntroStockAssessment) VLAB was created under the D4Research Virtual Organisation for an ICES training course

In T4.3

  • 5 new users registered to the BlueBRIDGE VREs: BlueBRIDGE Project (2), Performance Evaluation in Aquaculture(2), Strategic Investment Analysis (1)
  • 44 users have been registered to the BlueBRIDGE VLAB: AnalyticsLab (5), AquacultureTrainingLab (3), BiodiversityLab (3), Bionym (1), FAO Tuna Atlas (5), RPrototypingLab (2), RStudioLab (13), Scalable Data Mining (2), SIASPA (2), TabulardataLab (2), VME-DB (1), ICES training course: Introduction to Stock Assessment (8)
  • Support requests: 29 tickets have been created, 35 tickets have been managed, 31 tickets have been closed

In T4.4

  • integration and testing of gCube 4.4.0. The release has been closed on April 30th
  • extensive clean-up of the release (100 obsolete components removed)
  • set-up of the building environment to build with Java 8

#39 Updated by Gabriele Giammatteo about 2 years ago

May 2017 Activity

In T4.1

  • JVM on dev and preprod nodes has been upgraded to version 1.8 (#6309)
  • deployment of gCube 4.5.0 started on preprod for testing (#8213)

In T4.2

  • Blue-Datathon VLab was created under the D4Research VO. This Virtual Research Environment is conceived for supporting the datathon event co-organised by the RDA-Europe and BlueBRIDGE from June 15 to 16, 2017, in Heraklion, Crete, Greece.

In T4.3

  • 4 new users have been registered to the BlueBRIDGE VREs: BlueBRIDGE Project (3), Protected Area Impact Maps (1)
  • 88 users have been registered to the BlueBRIDGE VLAB : AnalyticsLab (7), AquacultureTrainingLab (3), BiodiversityLab (11), Bionym (2), FAO Tuna Atlas (5), InfraTraining (4), iSearch (3), RPrototypingLab (9), RStudioLab (3), Scalable Data Mining (5), SIASPA (2), TabulardataLab (3), ICES training course: Introduction to Stock Assessment (25), ICES Training course: Introduction to abundance estimation from fisheries acoustic surveys(6)
  • support requests managed: 31 tickets have been created, 34 tickets have been managed, 33 tickets have been closed

In T4.4

  • release gCube 4.5.0 started on May, 2nd (Smartgear #8211, gCore #8212, functional tests #8213)
  • Migration to Java 8
    • integration of gCube switched to Java 8 for Smartgears release in ETICS (while gCore components are still in Java 7)
    • integration tools have been updated to allow fine grain control on which Java version to use for the compilation
    • wiki updated with migration issues and guidelines :https://wiki.gcube-system.org/gcube/GCube_Java_8_migration_guide

#40 Updated by Gabriele Giammatteo almost 2 years ago

June 2017 Activity

In T4.1

  • JVM on production nodes has been upgraded to version 1.8
  • preproduction and production infrastructures upgraded with gCube 4.5.0
  • Refactored the gcube enabling services ansible roles and the orchestrator a bit to make it easier to keep working on integrating other roles. (#8394)

In T4.2

  • on June 4th VLab created under the D4Research Virtual Organisation for the ICES training course Introduction to abundance estimation from fisheries acoustics, 12–16 June 2017, ICES Secretariat, Copenhagen, Denmark

  • on June 29th MARKELLOS_Aquaculture VRE was created under the FARM Virtual Organisation. This Virtual Research Environment is conceived to provide the MARKELLOS aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis. Access to this working environment is restricted to MARKELLOS members only.

  • on June 29th STRATOS_AQUACULTURES VRE was created under the FARM Virtual Organisation. This Virtual Research Environment is conceived to provide the STRATOS aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis. Access to this working environment is restricted to STRATOS members only.

  • 3 VREs dedicated to the WP6 SMEs have been moved from the gCubeApps VO to the FARM VO see Task #9074 :
    /d4science.research-infrastructures.eu/gCubeApps/EllinikaPsariaVRE
    /d4science.research-infrastructures.eu/gCubeApps/ForkysVRE
    /d4science.research-infrastructures.eu/gCubeApps/AlieiaVRE

In T4.3

  • 3 users have been registered to the BlueBRIDGE VREs: Aquaculture Atlas Generation (1), Protected Area Impact Maps (2)
  • 113 users have been registered to the BlueBRIDGE VLAB: AnalyticsLab (10), BiodiversityLab (1), Bionym (3), Ellinika Psaria VRE (2), FAO Tuna Atlas (1), Forky’s VRE (1), InfraTraining (1), RPrototypingLab (3), RStudioLab (2), Scalable Data Mining (3), ICES training course: Introduction to Stock Assessment (1), ICES Training course: Introduction to abundance estimation from fisheries acoustic surveys(30), MARKELLOS_Aquaculture (5), STRATOS_AQUACULTURES (6), Blue-Datathon(44)
  • support requests managed: 46 tickets have been created, 45 tickets have been managed, 44 tickets have been closed;

In T4.4

  • release gCube 4.6.0 started on June, 12th (Smartgear #8545, gCore #8811, functional tests #8814). It should end on July 20th.
  • continue the clean-up of the obsolete components and started to contact the developer to ask if possible to upgrade to Java8 their configuration component as discussed during the last 5th TCOM (https://goo.gl/koMlsC)
  • Continues the Git-Hub migration activities. As announced in the last 5th TCOM ENG started with the migration of their own components to resolve and analyze and describe the migration steps to share with the rest of the partners

#41 Updated by Gabriele Giammatteo almost 2 years ago

July (M23) and August (M24) 2017 Activity

In T4.1

  • preproduction and production infrastructures upgraded with gCube 4.6.0

In T4.2

  • "Introduction to the R Environment VRE" (VLab) was created under the D4Research Virtual Organisation and used during an ICES training course held the 21–25 August 2017 ICES, Copenhagen, Denmark
  • "Introduction to Management Strategy Evaluation VRE" (VLab) was created under the D4Research Virtual Organisation and used during an ICES training course to the Management Strategy Evaluation 28 August–1 September 2017 ICES, Copenhagen, Denmark
  • the "Aquabiotech" and "StatnMap" VREs have been created under the FARM Virtual Organisation. They have been created for the two companies "AquaBioTech" and "StatnMap" (two of the five winners of the BlueBRIDGE Competitive Call for SMEs). They are designed to support small and medium enterprises in improving their data management practices thus paving the way for enhanced data products and services

In T4.3

  • 7 new users have been registered to the BlueBRIDGE VREs: Aquaculture Atlas Generation (2), BlueBRIDGE-PSC (1), BlueBRIDGE Project (2), Protected Area Impact Maps (1), Stock Assessment (1)
  • 114 users have been registered to the BlueBRIDGE VLAB: BiodiversityLab (5), Bionym (6), FAO Tuna Atlas (3), Forky’s VRE (1), GRSF_Admin (1), iSearch(2), RPrototypingLab (13), RStudioLab (1), Scalable Data Mining (10), TabulardataLab (7), ICES_MSE (27), Aquabiotech (8), ICES_IntroToREnv (30)
  • support requests managed: 52 tickets have been created, 58 tickets have been managed, 57 tickets have been closed

In T4.4

  • gCube 4.6.0 integration started on June, 12nd (Smartgear #8545, gCore #8811, functional tests #8814). Due to the serious problem with the ETICS portal, the ENG team set-up a temporary building environment and executed manually the builds of the components. Since this required considerable effort, the release plan has been reviewed and it has been decided to keep only a subset of the expected components in the release (higher priority was assigned to the Community Apps components)
  • gCube 4.6.0 has been closed on the 25th of July and all components excluded have been postponed to gCube 4.6.1 (end of August)
  • at the end of July, issues with ETICS have been solved and the status of the configurations have been synchronized with the status of the release
  • gCube 4.6.1 integration started on July 25th (Smartgear #9255, gCore #9390, functional tests #9399) in ETICS. This release contains all the components excluded from gCube 4.6.0 (enabling and common components)
  • Functional tests on gCube 4.6.1 will start on 1st of September and it will be deployed in production on Sept 11st
  • release 4.7.0 started on 28th August (Smartgear #9397, gCore #9398, functional tests #9399)

#42 Updated by Gabriele Giammatteo over 1 year ago

September 2017 Activity

In T4.1

  • Pre-production and production infrastructures have been updated to the latest gCube release 4.6.1;

In T4.2

  • 3 VLabs have been created (GALAXIDI VRE, ARDAG_Aquaculture VRE and iLKNAK_Aquaculture VRE) for three aquaculture companies. These environments provide their members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis. Access to this working environment is restricted to the company's members only.
  • the IOTC_SS3 VRE was created. This VLAB is conceived to provide a tool that hosts codes necessary to run the Stock Synthesis version 3 (SS3) stock assessment model (a widely-used statistical catch-at-age model), parallelise, visualize and store the standardized data outputs, make projections, and automate the reporting. The VRE enables any user to easily parameterize, execute and edit online various steps of the stock assessment work flow. It provides several collaborative web services, including: (i) a workspace to share documents or data, (ii) an RStudio server to process data online, and (iii) an automated reporting service to dynamically generate documents to package the results. Contact person: Julien Barde (IRD)

In T4.3

  • 3 new users have been registered to the BlueBridge VREs: Aquaculture Atlas Generation (1), Knowledge Bridging (1), Stocks & Fisheries Knowledge Base (1);
  • 68 new users have been registered to the BlueBRIDGE VLABs: Alieia VRE (1), AnalyticsLab (24), BiodiversityLab (2), GRSF_Admin (2), ICCAT_BFT-E (2), ICES_TCRE (1), InfraTraining (1), RPrototypingLab (3), RStudioLab (1), TabulardataLab (4), GALAXIDI (6), IOTC_SS3 (13), ARDAG_Aquaculture (4), iLKNAK_Aquaculture (4);

In T4.4

  • gCube 4.6.1 integration of all componets excluded from the #4.6.0 continues and was closed on September 19 (Smartgear #9255, gCore #9390, functional tests #9297). In total 82 (13 new, 63 updated and 3 removed) components modified and 17 subsystem updated. The closure of the release has been delayed (originally planned for Sept, 4th) due to integration issues on some components (#9679);
  • gCube 4.7.0 integration started on 28 August (Smartgear #9397, gCore #9398, functional tests #9774). All components planned in this release are integrated. The functional test started on the last week of September and will be closed on October 4th, the roll-out is on October 5th.

#43 Updated by Maria Di Girolamo over 1 year ago

  • Due date changed from May 28, 2017 to Oct 12, 2017

due to changes in a related task

#44 Updated by Maria Di Girolamo over 1 year ago

  • Due date changed from Oct 12, 2017 to May 28, 2017

due to changes in a related task

#45 Updated by Gabriele Giammatteo over 1 year ago

October 2017 Activity

In T4.1

  • release gCube 4.7.0 has been deployed in production
  • pre-production and production infrastructures have been upgraded with gCube 4.7.1

In T4.2

  • ICES_LogbookData VRE (VLab) was created (#6828) under the D4Research Virtual Organisation. This Virtual Research Environment is conceived for an ICES training course on VMS and EU logbook data , 23 – 27 October​ 2017, ICES, ICES Secretariat, Copenhagen, Denmark
  • KIMAGRO_Fishfarming VRE was created (#9916) under the FARM Virtual Organisation. This Virtual Research Environment is conceived to provide the KIMAGRO_Fishfarming aquaculture company members with a set of aquafarming assessment tools enacting them to perform evaluation growth analysis and techno economic investment analysis. Access to this working environment is restricted to KIMAGRO_Fishfarming members only
  • ICES_FIACO2017 was created (#10009) under the D4Research Virtual Organisation. This VREs conceived to support the ICES training course on "Principles and methods of broadband/wideband technologies: application to fisheries acoustics", going to be held on 8 – 12 December 2017 , Bergen, Norway
  • ICES_BNetworkAnalysis was created (#6829) under the D4Research Virtual Organisation. This VREs conceived to support the ICES training course on "Bayesian Network analysis including the socio-cultural dimension ", going to be held on 27th November to 1st December in ICES HQ, Copenhagen, Denmark​

In T4.3

  • 5 users have been registered to the BlueBRIDGE VREs: Blue Commons (1), Blue Uptake (2), Protected Area Impact Maps (2)
  • 125 users have been registered to the BlueBRIDGE VLAB : AnalyticsLab (5), Aquaculture Training Lab (1), BiodiversityLab (5), Bionym (1), GRSF_Admin (2), ICCAT_BFT-E (1), RPrototypingLab (11), ScalableDataMining (2), SIASPA (3), TabulardataLab (6), IOTC_SS3 (18), ARDAG_Aquaculture (1), iLKNAK_Aquaculture (1), KIMAGRO_Fishfarming(4), ICES_LogbookData (25), ICES_FIACO2017(27), ICES_BNetworkAnalysis(17)
  • 34 support requests have been managed, 35 tickets have been closed;

In T4.4

  • mainteneance release gCube 4.7.1 (from 16th to 18th October) has been integrated to fix multiple user groups assignment and email formatting in the user management portlet (#9961)
  • gCube 4.8.0 release integration started on October 11th (Smartgear #9723, gCore #9884, functional tests #9885). All components of the three groups can be implemented and integrated. The release should be closed on November 21th
  • a new configuration has been added in the gCube Maven configuration to create uberjar artifacts (a jar that embeds its dependencies) during the building process (#10089). A similar approach is being implemented for the servicearchives. This allows to reduce errors and non-compliant configurations in the building of gCube software artifacts

#46 Updated by Gabriele Giammatteo over 1 year ago

November 2017 Activity

In T4.1

  • Pre-production and production infrastructures have been updated to the latest gCube release 4.8.0. #10073

In T4.2

  • Sinay VRE (VLab) was created to support one of the winner of the BlueBRIDGE Competitive Call for SMEs. This VRE aims at producing model-based habitat maps of cetaceans produce model-based noise footprint maps of selected offshore activities assess risk and potential impacts.
  • SDG-Indicator14.4.1 VRE (VLab) was created for supporting the FAO training workshop on "Best-practices for the implementation and reporting of SDG Indicator 14.4.1 - Percentage of biologically sustainable fish stocks" by Dr. Yimin YE, FAO FIAF Branch Chief at FAO Headquarters – India Room - November 21 to 24, 2017. The VRE provides access to a Web tool supporting the application of several stock assessment models through a unique interface, using a Cloud computing service behind the scenes.

In T4.3

  • 30 users have been registered to the BlueBRIDGE VREs (totalling to 459): BlueBRIDGE-EAB (3), Protected Area Impact Maps (26), StockAssessment (1)
  • 171 users have been registered to the BlueBRIDGE VLAB (totalling to 2186): AnalyticsLab (10), Aquaculture Training Lab (65), BiodiversityLab (13), Bionym (4), FAO_TunaAtlas (2), iSearch (2), RPrototypingLab (11), RStudioLab (5), ScalableDataMining (9), SIASPA (3), TabulardataLab (4), Blue-Datathon (1), ICES_IntroToREnv (1), IOTC_SS3 (3), ARDAG_Aquaculture (1), iLKNAK_Aquaculture (1), ICES_BNetworkAnalysis(3), SDG-Indicator14.4.1 (27), Sinay (6)
  • 38 support requests (tickets) have been created, 46 have been managed and 38 have been closed

In T4.4

  • integration of gCube 4.8.0. The release has been closed on November 29th with one week delay. This release contains: 4 new components, 47 updated components in 18 different subsystems
  • integration of gCube 4.9.0 started on November 29th. It will be closed on December, the 19th

#47 Updated by Gabriele Giammatteo over 1 year ago

December 2017 Activity

In T4.1

  • Pre-production and production infrastructures have been upgraded to the latest gCube release 4.9.0. #10585

In T4.2

  • CWP-Secretariat VRE (VLab) was created under the FARM Virtual Organisation. The VRE is conceived to support the development and maintenance of the Catalog of the Coordinating Working Parties on Fisheries Statitics, a catalog initiated upon recommendations from the CWP ad-hoc Task Group on reference data harmonization. The catalog is a listing of available CWP global DSDs, CWP standards, and codelists used by CWP parties and other resources. The catalog will be updated routinely updated by FAO, the CWP secretariat.

  • SustainableBlueEconomy VRE (VLab) was created under the FARM Virtual Organisation. The VRE is conceived to showcase the potential and dynamics of the Blue Economy Tools to policy makers, stakeholders and investors through a collaborative environment.

In T4.3

  • 3 new users registered to the BlueBRIDGE VREs (totalling to 462): Aquaculture Atlas Generation (2), Protected Area Impact Maps (1)
  • 186 users have been registered to the BlueBRIDGE VLAB (totalling to 2372): AnalyticsLab (6), Aquaculture Training Lab (137), BiodiversityLab (5), Bionym (2), GRSF Admin(2), iSearch (1), RPrototypingLab (4), RStudioLab (1), ScalableDataMining (3), SIASPA (4), TabulardataLab (2), MARKELLOS_Aquaculture (1), IOTC_SS3 (2), Sinay (2), SustainableBlueEconomy(8), CWP-Secretariat (6)
  • 28 support tickets have been created, 32 tickets have been managed and 31 have been closed

In T4.4

  • integration of gCube 4.9.0 finished and the release has been closed on December 19th 2017. This release contains: 3 new components and 35 updated components in 11 different subsystems
  • release gCube 4.10.0 started on 18 December 2017. This will be the latest BlueBridge project release and will be closed on February 12nd
  • TOC for D4.4 has been produced

#48 Updated by Maria Di Girolamo over 1 year ago

  • Due date changed from Nov 10, 2017 to Feb 12, 2018

due to changes in a related task

#49 Updated by Gabriele Giammatteo over 1 year ago

January 2018 Activity

In T4.1

  • Pre-production infrastructure have been upgraded with gCube release 4.10.0 to start the functional testing of the release

In T4.2

  • SDI_LAB VRE (VLab) was created to support a workshop gathering data managers (around 30 people) from different french institutes (CNRS, INRA, IRD) to discuss methods to set up a workflow for spatial metadata, data and related services

  • FrenchTropicalTunaAtlas VRE (VLab) was to support sharing of french tropical tuna fisheries data between the Observatory of Exploited Tropical Pelagic Ecosystems (Ob7) of the IRD and the french Ministry of fisheries (DPMA)

In T4.3

  • 12 new users registered to the BlueBRIDGE VREs: BlueBRIDGE Project(1), Protected Area Impact Maps (11);
  • 115 new users registered to the BlueBRIDGE VLAB: AnalyticsLab (4), Aquaculture Atlas Generation (7), Aquaculture Training Lab (5), BiodiversityLab (8), Bionym (3), FAO Tuna Atlas (4), GRSF Admin(1), ICCAT_BFT-E (1), RPrototypingLab (9), RStudioLab (4), ScalableDataMining (3), SIASPA (5), TabulardataLab (3), IOTC_SS3 (1), Sinay (2), SustainableBlueEconomy(30), SDI_Lab (28), FrenchTropicalTunaAtlas (5);
  • 40 support requests have been reported and 39 requests have been managed in this month;

In T4.4

  • continued the integration of the gCube 4.10.0 (Smartgear: #10687, gCore: #10727, FT Testing: #10728) and started with testing. No relevant issue are report
  • preparation of the 7th TCOM meeting;
  • finalized the deliverable D4.4 and sent to the internal review (#637)

#50 Updated by Maria Di Girolamo about 1 year ago

  • Due date changed from Feb 12, 2018 to Mar 30, 2018

due to changes in a related task

#51 Updated by Pasquale Pagano about 1 year ago

  • Status changed from In Progress to Closed