Task #1340

Move CITE's OpenSource code into a separate publicly accessible repository

Added by George Kakaletris over 3 years ago. Updated over 1 year ago.

Status:ClosedStart date:Nov 11, 2015
Priority:NormalDue date:Jan 20, 2016
Assignee:Kostas Kakaletris% Done:

100%

Category:-
Sprint:WP04
Infrastructure:Development, Pre-Production, Production
Milestones:
Duration: 51

Description

Provide public access to FOSS components through an unauthenticated access repository.


Related issues

Related to BlueBRIDGE - Project Task #656: T6.2 Strategic Investment analysis and Scientific Plannin... Closed Oct 01, 2015 Feb 28, 2018
Related to BlueBRIDGE - Project WP #697: WP10 - Interfacing Infrastructures [Months: 1-30] Closed Mar 07, 2016 Jun 01, 2017
Related to BlueBRIDGE - Project WP #629: WP4 - VREs Deployment and Operation [Months: 1-30] Closed Aug 03, 2015 Mar 30, 2018

History

#1 Updated by George Kakaletris over 3 years ago

  • Related to Project Task #656: T6.2 Strategic Investment analysis and Scientific Planning/Alerting VRE [Months: 1-30] added

#2 Updated by George Kakaletris over 3 years ago

  • Related to Project WP #686: WP9 - VRE Commons Development [Months: 1-30] added

#3 Updated by George Kakaletris over 3 years ago

  • Related to Project WP #697: WP10 - Interfacing Infrastructures [Months: 1-30] added

#4 Updated by Kostas Kakaletris over 3 years ago

  • % Done changed from 0 to 20
  • Status changed from New to In Progress

#5 Updated by Kostas Kakaletris over 3 years ago

  • Due date changed from Nov 30, 2015 to Dec 31, 2015

#6 Updated by Kostas Kakaletris over 3 years ago

  • % Done changed from 20 to 60
  • Due date changed from Dec 31, 2015 to Jan 20, 2016

#7 Updated by Massimiliano Assante over 3 years ago

I see this ticket related to WP4 rather than WP9 or WP10. Am I getting this wrong?

#8 Updated by Massimiliano Assante over 3 years ago

  • Related to deleted (Project WP #686: WP9 - VRE Commons Development [Months: 1-30])

#9 Updated by Massimiliano Assante over 3 years ago

  • Related to Project WP #629: WP4 - VREs Deployment and Operation [Months: 1-30] added

#10 Updated by Kostas Kakaletris over 1 year ago

  • % Done changed from 60 to 100
  • Status changed from In Progress to Closed
  • Infrastructure Development, Pre-Production, Production added

CITE's OpenSource code is published along with the rest of the project's source code in GitHub (https://github.com/gcube-team/gcube-releases)